Question: In enterprise resources planning ( ERP ) system manufacturing modules, the result of master scheduling is the master production schedule ( MPS ) , which
In enterprise resources planning ERP system manufacturing modules, the result of master scheduling is the master production schedule MPS which is evaluated for constraints by which of the following?
Answers
Roughcut capacity planning RCCP
Integrated process control
Distribution requirements planning DRP and capacity requirements planning CRP
Material requirements planning MRP