Question: In Excel, this is tab Prob 2 . Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the
In Excel, this is tab Prob
Kelle Carpet and Trim installs carpet in commercial offices.
Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs.
Some of his workers are very unreliable.
A list of activities and time estimates for a new contract are given in the table.
a pts Draw ON PAPER an AON for this project.
b pts Find the critical path.
c pts Compute expected project completion time.
d pts Compute the project variability.
e pts What is the probability the project will be completed between and days.