Question: In formulating an LP model for this network: How many decision variables are required? Besides non - negativity constraints, how many constraints are required? The

In formulating an LP model for this network:
How many decision variables are required?
Besides non-negativity constraints, how many constraints are required?
The constraint for supply node 1 is:
xA1+xB1+xC1=670
9x1A+7x1B+7x1C=670
x1A+x1B+x1C<=670
9x1Ax7x1B+7x1C<=670
x1A+x1B+x1C=670
The constraint for demand node B is:
7x1B+9x2B+8x3B<=500
xB1+xB2+xB3=500
x1B+x2B+x3B=500
x1B+x2B+x3B<=500
7x1B+9x2B+8x3B=500

Step by Step Solution