Question: In lean-based projects using the Last Planner System, what does the Percent Plan Complete (PPC) measure? Question 2Select one: A. The deviation from the planned
In lean-based projects using the Last Planner System, what does the Percent Plan Complete (PPC) measure? Question 2Select one: A. The deviation from the planned outcome at defined intervals. B. The reliability of the involved actors. C. The ratio of total cost expended to date over total estimated cost. D. The overall project's total estimated cost