Question: In making project trade - offs, a criterion that is allowed not to meet the original target, for example, allowing the schedule to slip, is

In making project trade-offs, a criterion that is allowed not to meet the original target, for example, allowing the schedule to slip, is classified as ___________.
a
enhanced
b
accepted
c
constrained
d
static
e
unchangeable

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!