Question: In making project trade - offs, a criterion that is allowed not to meet the original target, for example, allowing the schedule to slip, is

In making project trade-offs, a criterion that is allowed not to meet the original target, for example, allowing the schedule to slip, is classified as ___________.
Question 13 options:
enhanced
accepted
constrained
static
unchangeable