Question: In MRP , scheduled receipts are: Select one: a . identical to planned - order receipts b . identical to planned - order releases c
In MRP "scheduled receipts" are:
Select one:
a
identical to "plannedorder receipts"
b
identical to "plannedorder releases"
c
open orders that is ordered before the first time bucket, but not delivered yet
d
"net requirements"
e
available to promise inventor