Question: In optimizing the plan, Jose wants to display a deadline marker on March 7, 2023 on the milestone task, Event location complete. If Lawal

In optimizing the plan, Jose wants to display a deadline marker on 

In optimizing the plan, Jose wants to display a deadline marker on March 7, 2023 on the milestone task, Event location complete. If Lawal takes 8d to complete the task called, Identify potential locations, what happens? 1 2 3 4 5 6 7 Task Mede 4 4 C 4 4 4 Task Name 4 Fvent Location Identify potential locations Prepare notes on locations Choose location Reserve location - Duration 9 days 5 days 1 day 1 day 1 day Sign location contract and pay deposit 1 day Event location complete 0 days Start Finish Thu 23/02/2: Tue 07/03/2 Thu 23/02/2: Wed 01/03/2 Thu 02/03/2. Thu 02/03/2: 2 Fri 03/03/23 Fri 03/03/23 3 Predecessors Mon 06/03/2 Mon 06/03/24 Tue 07/03/2: Tue 07/03/25 Tue 07/03/2: Tue 07/03/2: 6 Resource Names Lawal 19 Feb 23 25 Feb 23 TFSSMTWTFSSMTWTFSSMTWTFS 05 Mar 23 Lawal The deadline marker falls before the milestone date and a caution indicator appears in the Indicators column. 07/03 The milestone date stays put on March 7, but the green deadline marker moves before the milestone date. The milestone date and the deadline marker do not move. Negative slack bars do not appear as the milestone date will still be met.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

If Lawal takes 8 days to complete the task Identify potential locations it means he will finish this ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!