Question: In order to avoid project delays, project managers confronted with a resource overload will seek to delay some of the noncritical activities by an amount

In order to avoid project delays, project managers confronted with a resource overload will seek to delay some of the noncritical activities by an amount no more than their slack period, to level the demand for that worker.Question 3 Select one:TrueFalse