Question: In PERT, the expected project duration will never exceed the expected duration of the critical path. True False Question 7 1 p t s Once
In PERT, the expected project duration will never exceed the expected duration of the critical path.
True
False
Question
Once a project is approved and underway, project managers are only responsible for effectively managing time and costs which, if done well, will assure project completion on time and on budget.
True
False