Question: In preparing a request for a time extension, the project manager should outline all of the following except: Select one: a . no explanation is
In preparing a request for a time extension, the project manager should outline all of the following except:
Select one:
a no explanation is needed
b the reason for the delay in completion
c additional cost due to delay
d steps taken to attempt to return to the original deadline