Question: In Project Management in general and Software Project Management in particular, if we assume we can only assign ONE resource to an activity, and if

In Project Management in general and Software Project Management in particular, if we assume we can only assign ONE resource to an activity, and if we assume that a given project has many different activities with each activity having a different duration, dependency, and resources required (although multiple different activities may have the same duration, dependency, and resources required) If we assume the above, explain WITH JUSTIFICATION how those resources are assigned to this given project. The given project:

In Project Management in general and Software

The resources:

An Analyst at $100 per hour, three Designer/Coders at $120 per hour each, two Testers at $40 per hour each

Activities of a mobile application development project Resources Activity Code Activities Duration Dependencies required A Analysis & Specification 2 weeks Analyst B Design modules Summary Design Module A 1 1 week A Designer/Coder D Design Module B 2 weeks A Designer/Coder E Design Module C 1 week A Designer/Coder F Code modules Summary G Code Module A Estimate Designer/Coder H Code Module B 4 weeks D Designer/Coder 1 Code Module C 12 days E Designer/Coder J Test modules Summary K Test Module A 3 days G Tester L Test Module B 1 week Tester Test Module C Estimate 1 Tester N Integration & System Testing Estimate K,L,M. Tester 0 Acceptance Testing 1 week N (FS + 2 days) Analyst

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!