Question: In project planning, float is the amount of time a task can be delayed past its earliest start date without impacting the project. How
In project planning, float is the amount of time a task can be delayed past its earliest start date without impacting the project. How much float is allowed for tasks on the critical path?
Step by Step Solution
★★★★★
3.48 Rating (155 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Tasks on the critical path have zero float or slack Float is the amount of time a task can be del... View full answer