Question: In project planning, float is the amount of time a task can be delayed past its earliest start date without impacting the project. How

In project planning, float is the amount of time a task can 

In project planning, float is the amount of time a task can be delayed past its earliest start date without impacting the project. How much float is allowed for tasks on the critical path?

Step by Step Solution

3.48 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Tasks on the critical path have zero float or slack Float is the amount of time a task can be del... View full answer