Question: In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities? a . estimating activity durations
In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities?
aestimating activity durations
bsequencing activities
cplanning schedule management
ddefining activities