Question: In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities? a . estimating activity durations

In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities?
a.estimating activity durations
b.sequencing activities
c.planning schedule management
d.defining activities