Question: In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities? a . planning schedule management
In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities?
a planning schedule management
b sequencing activities
c defining activities
d estimating activity durations