Question: In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities? a . planning schedule management

In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities?
a. planning schedule management
b. sequencing activities
c. defining activities
d. estimating activity durations