Question: In Spring 2017, Bava Construction signed a contract with the city of Springfield, to construct a new city hall for $200 million. Bava expects to

In Spring 2017, Bava Construction signed a contract with the city of Springfield, to construct a new city hall for $200 million. Bava expects to construct the building within two years and incur expenses of $150 million, which means the company earns a $50 million profit on the contract. Bava incurred $60 million in costs during 2017 and $90 million in 2018 to complete the contract on time.

Using the cost-to-cost method, fill in the table below indicating how much revenue and profit Bava will recognize in both 2017 and 2018.

Year . Contract Sales . Percent completed . Revenue Recognized . Costs incurred (expenses) . Profit Recognized

2017 . $200 million $60 million

2018 $90 million

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!