Question: In Spring 2017, Bava Construction signed a contract with the city of Springfield, to construct a new city hall for $200 million. Bava expects to
In Spring 2017, Bava Construction signed a contract with the city of Springfield, to construct a new city hall for $200 million. Bava expects to construct the building within two years and incur expenses of $150 million, which means the company earns a $50 million profit on the contract. Bava incurred $60 million in costs during 2017 and $90 million in 2018 to complete the contract on time.
Using the cost-to-cost method, fill in the table below indicating how much revenue and profit Bava will recognize in both 2017 and 2018.
| Year | Contract Sales | Percent completed | Revenue Recognized | Costs incurred (expenses) | Profit Recognized |
| 2017 | $200 million |
|
| $60 million |
|
| 2018 |
|
| $90 million |
|