Question: In Table 3.2 of Project Management Example (please note: Table 3.2 is in the Project Management Example, PowerPoint slides; two changes are made: (i) Activity

In Table 3.2 of Project Management Example (please note: Table 3.2 is in the Project Management Example, PowerPoint slides; two changes are made: (i) Activity D, Pour Concrete and Install Frame 5 weeks, instead of 4 weeks; (ii) Activity H, Inspect and Test 3 weeks, instead of 2 weeks. Do the Revised Project Network Problem completely, show network figure, a table showing (ES, EF, LF, LS, ST), Critical Path, and Project Duration.
Perform a Critical Path/Analysis
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
