Question: In the approach described to develop a resource constrained schedule: I. If an activity is delayed due to a resource constraint, it may delay the
In the approach described to develop a resource constrained schedule: I. If an activity is delayed due to a resource constraint, it may delay the project. II. After scheduling according to precedence relationships, activities may have to compete for scarce resources. III. An activity's start time in the resource constrained schedule may be delayed beyond its early start time found using the Critical Path Method. IV. An activity's start time in the resource constrained schedule may be delayed beyond its late start time found using the Critical Path Method.
Group of answer choices
All of the above.
III and IV.
I and II.
I, II and III.