Question: In the basic EOQ model (under constant demand), weekly demand is 100 and lead time is 1 month . Assume 4 weeks per month. If
In the basic EOQ model (under constant demand), weekly demand is 100 and lead time is 1 month. Assume 4 weeks per month. If the company wishes to carry no safety stock, what should be the reorder point (ROP)?