Question: In the construction project example in the video, why did we stop crashing at Round 5? Group of answer choices Cost to crash further exceeds
In the construction project example in the video, why did we stop crashing at Round 5? Group of answer choices Cost to crash further exceeds the savings The critical path can no longer be shortened All tasks are at the minimum duration