Question: In the construction project example in the video, why did we stop crashing at Round 5? (or at what point you you stop crashing a
In the construction project example in the video, why did we stop crashing at Round 5?
(or at what point you you stop crashing a project)
Group of answer choices
The critical path can no longer be shortened
All tasks are at the minimum duration
Cost to crash further exceeds the savings