Question: In the construction project example in the video, why did we stop crashing at Round 5? (or at what point you you stop crashing a

In the construction project example in the video, why did we stop crashing at Round 5?

(or at what point you you stop crashing a project)

Group of answer choices

The critical path can no longer be shortened

All tasks are at the minimum duration

Cost to crash further exceeds the savings