Question: In the critical path method, if an activity has no logical sequence relationships then it can be connected to any activity the project manager selects.
In the critical path method, if an activity has no logical sequence relationships then it can be connected to any activity the project manager selects.
True or False
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
