Question: In the critical path method, the earliest start is the _______. a. Average of earliest finish leading into the task. b. Whenever the project manager
In the critical path method, the earliest start is the _______.
a. Average of earliest finish leading into the task.
b. Whenever the project manager wants the task to start.
c. The smallest earliest finish leading to that task
d. The largest earliest finish leading to that task.