Question: In the diagram, there are 2 rectangles. The one on the left is labeled S , and the one on the right is labeled F

In the diagram, there are 2 rectangles. The one on the left is labeled S, and the one on the right is labeled F. There are 10 circles labeled inside each circle using the letters from A to J. There is a number below the letter inside each circle. There are arrows that show the flow through the circles from S to F as follows: Rectangle S has arrows that connect to circles A 4, B 5, and C 3, circle A 4 connects to circle F 9, circle B 5 connects to circle D 3, to circle E 1, and to circle F 9, circle C 3 connects to circle F 9, circles D 3 and E 1 connect to circle G 3, circle F 9 connects to circle H 6 and to circle I 3, circles G 3, H 6, and I 3, connect to circle J 6, and circle J 6 connects to Rectangle F.
Part 3
b. Calculate the critical path for this project.
The critical path is
A-B-F-H-J
A-B-E-G-J
A-B-F-I-J
A-C-F-H-J
A-B-D-G-J
A-C-F-I-J
and the project duration is
enter your response here days. (Enter your response as a whole number.)
Part 4
c. How much slack is in each of the activities G, H, and I?
Activity
Activity
Time(days)
On critical path?
Slack
(days)
G
3
Yes
No
enter your response here
H
6
No
Yes
enter your response here
I
3
No
Yes
enter your response here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!