Question: In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more), and each time, the estimate for a particular activity is

 In the enumeration method the project schedule is calculated many times

In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more), and each time, the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager. True False