Question: In the enumeration method for determining the critical path, the project schedule is calculated many times ( perhaps 1 , 0 0 0 or more
In the enumeration method for determining the critical path, the project schedule is calculated many times perhaps or more and each time, the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager.
Group of answer choices
True
False