Question: In the following AON project network, the estimated normal durations for each task are indicated at each node. Each task in this project can be
In the following AON project network, the estimated normal durations for each task are indicated at each node. Each task in this project can be compressed by a maximum of two weeks; each weeks decrease will cost an amount that is equal to its estimated normal duration for example, the duration of task A can be reduced to six weeks by spending an additional $K or it can be reduced to five weeks for an additional cost of $K