Question: In the following network, try to reduce the maximum resource need to less than eight laborers per day. Can you do this? If not, can
In the following network, try to reduce the maximum resource need to less than eight laborers per day. Can you do this? If not, can you manually shift activities so that you improve the daily resource use? (We try to start low, increase the resource use gradually until it peaks around the middle of the project, and then gradually decrease it toward the end of the project.)
| Activity | Duration (Days) | IPA | Laborers |
| A | 6 | 2 | |
| B | 2 | 3 | |
| C | 8 | A | 3 |
| D | 5 | A, B | 5 |
| E | 3 | B | 4 |
| F | 6 | D, E | 3 |
| G | 5 | C, D | 2 |
| H | 2 | F, G | 3 |
In an Excel spreadsheet, demonstrate the activities before they are leveled and after they are leveled. Draw a network diagram representing the activities before leveling the resources, and one for after leveling the resources.
PLEASE REFERENCE ABOVE AS I NEED EXCEL TO SHOW BEFORE AND AFTER LEVELED. NOT JUST AFTER AS WELL AS NETWORK DIAGRAM FOR BEFORE AND AFTER LEVELING PLEASE AND THANKS!!!