Question: Problem 3 ( 3 5 Marks ) : In the following network, manually level your resources with a maximum of eight laborers per day. Also,

Problem 3(35 Marks): In the following network, manually level your resources with a maximum of eight laborers per day. Also, improve the daily resource use (start low, increase the resource use gradually until it peaks around the middle of the project, and then gradually decrease it toward the end of the project).
\table[[Activity,Duration (Days),IPA,Laborers],[A,6,-,2],[B,2,-,3],[C,8,A,3],[D,5,A,B,5],[E,3,B,4],[F,6,D,E,3],[G,5,C,D,2],[H,2,F,G,3]]