Question: In the following project network, the linear programming model that seeks to determine the latest start time of each activity will have constraints (not including

In the following project network, the linear

In the following project network, the linear programming model that seeks to determine the latest start time of each activity will have constraints (not including the non-negativity constraints). F 4 2 A 5 D 2 5 3 Legend B E H ID 3 5 2 Dur Select one: O a. 7 O b. none of the provided number O c. 9 O d. 5 O e. 11