Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working Activity Immediate Predecessor(s) Time (days) Carl's team should be able to complete the project in 21 days. CDEFO