Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction

In the following table the activities with their precedence sequence and expected

In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working Carf's team should be able to complete the project in days Activity Immediate Predecessor(s) Time (days) 5 4 6 6 B 4 4 G D 6 H E.F B