Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project a) The activities on the
In the following table the activities with their precedence sequence and expected time (days) are listed for a project a) The activities on the critical path are b) The project length is days Activity Immediate Predecessor(s) Time (days) ABCDERCH- 5 2 A 4 B B C E. F 5 5 D GH 6227 3 5