Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Predecessor(s) Time (days) A 6

In the following table the activities with their
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Predecessor(s) Time (days) A 6 B 2 C A 4 D B 5 E B 5 F C 5 G EF N H D 3 1 GH 7 Draw the network diagram and answer the following question: What is the critical path? O AC-FG-1 O A-B-E-G- A-B-D-H:1 O A-B-C-D-E