Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project XYZ company is working: Activity Immediate
In the following table the activities with their precedence sequence and expected time (days) are listed for a project XYZ company is working:
| Activity | Immediate Predecessors | Time (days) |
| A | - | 3 |
| B | A | 2 |
| C | - | 4 |
| D | B | 6 |
| E | B | 7 |
| F | C | 5 |
| G | D | 6 |
| H | E,F | 2 |
Draw an AON Diagram: 5 points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
