Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity A Immediate Predecessor(s) Time (days)

In the following table the activities with their
In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity A Immediate Predecessor(s) Time (days) 5 2 B C A A B 4 5 5 5 2 3 6 B EF D G H G H 1 a) The activities on the critical path are b) The project length is days. A-B-E-G-1 A-B-D-H-1 A-C-F. G-1