Question: In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian Fok's construction project and on the right

In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian Fok's construction project and on the right the precedence network is shown:

Activity

Nodes

Time (weeks)

J

1-2

12

K

1-3

8

L

2-4

6

M

2-3

3

N

3-4

4

O

4-5

7

P

3-5

7

1

3

K

2

M

4

5

J

L

O

N

P

In the diagram, there are 5 circles labeled using the numbers from 1 to 5. There are 7 arrows, and each arrow connects one circle to another circle. The arrows are situated in the following manner: Arrow J joins 1 to 2, Arrow K joins 1 to 3, Arrow L joins 2 to 4, Arrow M joins 2 to 3, Arrow N joins 3 to 4, Arrow O joins 4 to 5, and Arrow P joins 3 to 5.

Part 2

The project length is

2626

weeks.

Part 3

The activities on the critical path are

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!