Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project XYZ company is working: Activity Immediate
- In the following table the activities with their precedence sequence and expected time (days) are listed for a project XYZ company is working:
| Activity | Immediate Predecessors | Time (days) |
| A | - | 3 |
| B | A | 2 |
| C | - | 4 |
| D | B | 6 |
| E | B | 8 |
| F | C | 5 |
| G | D | 6 |
| H | E,F | 1 |
Draw an AON Diagram: 5 points
- Time for team to complete is _______________days.
b. Critical path(s) _______________.