Question: In the following table the activities with their precedence sequence and expected time (weeks) are listed for a project: Activity Immediate Predecessors Time (weeks) 4

In the following table the activities with their

In the following table the activities with their precedence sequence and expected time (weeks) are listed for a project: Activity Immediate Predecessors Time (weeks) 4 B 3 2 C D A A E F B B 1 4 6 G C, E E, F ONO 7 . 6 Draw an AON Diagram a. a. Fill in all green boxes of the following chart. EF LS Activity Time ES weeks LF Slack Critical Path Yes or No B Ula E F G H . a. Critical path is b. Total project completion time is weeks