Question: In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian Fok's construction project and on the
In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian Fok's construction project and on the right the precedence network is shown: Activity J KLMNOP Nodes 1-2 1-3 2-4 2-3 3-4 4-5 3-5 The project length is weeks. Time (weeks) 10 8 63477 K M N/ P 5 Q 27