Question: In the following table, the project activity durations are given in weeks along with their predecessor relationships. For example, activity A can start anytime, as

In the following table, the project activity durations are given in weeks along with their predecessor relationships. For example, activity A can start anytime, as it does not have any predecessor. But activity B can start only when activity A is complete; so is activity C. Use Microsoft Excel for answering the following questions.

Activity

Duration

Predecessor

A

4

None

B

6

A

C

4

A

D

2

C

E

4

B

F

5

B, D

G

3

C

H

4

F, G

I

2

E, H

a) Construct the network diagram. (NEED TO BE DONE ON EXCEL)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!