Question: In the following table, the project activity durations are given in weeks along with their predecessor relationships. For example, activity A can start anytime, as
In the following table, the project activity durations are given in weeks along with their predecessor relationships. For example, activity A can start anytime, as it does not have any predecessor. But activity B can start only when activity A is complete; so is activity C. Use Microsoft Excel for answering the following questions.
| Activity | Duration | Predecessor |
| A | 4 | None |
| B | 6 | A |
| C | 4 | A |
| D | 2 | C |
| E | 4 | B |
| F | 5 | B, D |
| G | 3 | C |
| H | 4 | F, G |
| I | 2 | E, H |
a) Construct the network diagram. (NEED TO BE DONE ON EXCEL)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
