Question: In the graph below, the critical path is ADEH. You will gain additional revenues of $800 per day, for every additional day earlier we finish

In the graph below, the critical path is ADEH.

In the graph below, the critical path is ADEH. You will gain additional revenues of $800 per day, for every additional day earlier we finish the project. It costs $500 for each day that we crash D. You can crash D as many as 7 days. 1. How many days is it optimal to crash D? 2. How much additional profit do you get from this crashing? B 5 (C 5 A 8 H7 D8 E6 HTML Editor