Question: In the network diagram given below activity C can be started only after activities A and B are complete. If there is an 80% chance
In the network diagram given below activity C can be started only after activities A and B are complete. If there is an 80% chance that activity A takes 3 days to complete and a 90% chance that activity B takes 4 days to complete, what is the probability that activity C can start on day 57 80% (day 1-3) (day 59) (day 1-4) 90% O 72% 80% 90% 170%