Question: In the PERT project scheduling technique each activity requires three times estimates (optimistic, most likely and pessimistic) so that the expected time can be calculated.

In the PERT project scheduling technique each activity requires three times estimates (optimistic, most likely and pessimistic) so that the expected time can be calculated. Assuming a beta probability distribution (like the provided diagram) for an individual project activity which of the following statements is true?

In the PERT project scheduling technique each activity requires three times estimates

Probability Pessimistic Optimistic I Most likely m

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!