Question: In the PERT project scheduling technique each activity requires three times estimates (optimistic, most likely and pessimistic) so that the expected time can be calculated.
In the PERT project scheduling technique each activity requires three times estimates (optimistic, most likely and pessimistic) so that the expected time can be calculated. Assuming a beta probability distribution (like the provided diagram) for an individual project activity which of the following statements is true?

Probability Pessimistic Optimistic I Most likely m
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
