Question: In the pictured assembly line, numbers indicate time in seconds. It is known that for a particular production setup the cycle time is 1 1
In the pictured assembly line, numbers indicate time in seconds. It is known that for a particular production setup the cycle time is seconds. Answer the following questions:
i What would be the throughput output rate of the process per workday hour workday with such cycle time?
ii For that particular production setup, what would be the theoretical minimum number of workstations?
iii If you balance the line for the needed cycle time using the longest task time first rule, what would be the total idle time?
iv What would be the line balance delay after such balancing?