Question: In the precedence diagramming method the triangle nodes means a decision must be made in the project. lags and leads unnecessarily cause complications. relationships between
In the precedence diagramming method the triangle nodes means a decision must be made in the project. lags and leads unnecessarily cause complications. relationships between activities are important activity details are usually not visible