Question: in the process of performing Validate Scope with the key stakeholders in order to sign off on the first set of project deliverables. In the
in the process of performing "Validate Scope" with the key stakeholders in order to sign off on the first set of project deliverables. In the meeting, two managers for key stakeholders have a difference of opinion on the deliverable requirements and refuse to sign off. Approach = Adaptive (Agile)
Step by Step Solution
There are 3 Steps involved in it