Question: In the table below the activities, dependencies and durations are given find the following A-Draw the Gantt Bar Chart for the activities B-Draw the network

In the table below the activities, dependencies

In the table below the activities, dependencies and durations are given find the following A-Draw the Gantt Bar Chart for the activities B-Draw the network diagram (AON) and find ES,EF,LS,LF,TF,FF, of the activities C-Find the project duration and show the Critical path Dependency Activity A B D E Duration (days) 10 7 5 ES D EF A,D B 4 B 6 Act FF. F E 3 G D 5 LS TE LE 9 H K L C,G F,G K 4 2