Question: In the time cost optimisation using CPM method of network analysis, the crushing of the activities along the critical path is done starting with activity

In the time cost optimisation using CPM method of network analysis, the crushing of the activities along the critical path is done starting with activity having (a) longest duration. (b) highestcostslope. (c) least cost slope. (d) shortest duration.